RAAF Amberley Civil Works

Client: Duratec Limited

RAAF Amberley Civil Works

 

Pentacon is the principal contractor for the design & construction of pavement improvement works to Purga Road Fire Track - 1400m.

 
  • Site management, traffic management, community liaison, environmental and erosionmanagement, safety and quality management

  • Clearing, grubbing and stripping of topsoil and stockpiling

  • Excavation of unsuitable material from firetrack formation

  • Ground surface treatment under pavement

  • Grading and reconstruction of fire track

  • Construction of all weather rock crossing points at floodway location

  • Drainage works including table drain

  • Supply and install floodway crossing including rockfill and pipework

Next
Next

Amberley 25M Range Works