Greenswamp Rd Bridge Upgrade, Charleys Creek

Client: Western Downs Regional Council

Greenswamp Rd Bridge Upgrade, Charleys Creek

 

Pentacon was principal contractor & work scope was to construct a two lane single span concrete bridge.

 
  • Upgrade of existing side track

  • Demolition and removal of existing timber bridge

  • Construction of new single span concrete bridge 21m total length on driven precast piles

  • Rock protective treatments

  • Bridge barrier and guardrail installaion

  • Stormwater drainage installation

  • Earthworks and road pavement construction to bridge approaches

  • Bitumen sealing of pavement