Tchanning Creek Timber Bridge Replacement
Client: Department of Transport and Main Roads
Tchanning Creek Timber Bridge Replacement
Pentacon was the principal contractor for the replacement of Tchanning Creek Bridge, including demolition.
The project consisted of the below:
Roadworks Work Package
Drainage, retaining structures and protective treatments;
Installation of culverts;
Clearing and grubbing;
Insitu stabilised pavements;
Sprayed bituminous treatments;
Road furniture;
Landscape and revegetation works;
Linemarking.
Bridgeworks Work Package
Erosion and sediment control;
Drainage, retaining structures and protective treatments;
General earthworks;
Driven steel piles;
Erection of prestressed concrete deck and kerb units;
Bridge deck;
Bridge barrier installation;
Deck wearing surface;